Batched processing of generation connection applications

Ireland processes generation, storage and system-service connection applications in batches twice a year, so operators can study how projects affect each other.

About this good practice

In September 2024, Ireland’s energy regulator, the Commission for Regulation of Utilities (CRU), decided that applications to connect new generators, storage and system-service projects to the grid would be processed in batches instead of one by one. Applicants can submit at any time before a batch closing deadline, set twice a year. EirGrid, which operates the transmission grid, and ESB Networks, which operates the distribution grid, check the applications, publish the list of qualifying projects and then study the batch together, so they can see how projects affect each other. Projects must show they are ready: non-renewable projects need planning permission before applying, while renewable and co-located storage projects, covered by the EU Renewable Energy Directive (RED III), need a completed planning application and a non-binding technical pre-assessment from the operator. System operators are required to issue connection offers for renewable projects within 12 months of the batch deadline, and for conventional projects within 18 months. This keeps unready projects out of the queue and makes connection studies more efficient. The policy is in force and covers generation, storage and system services, but not demand connections.