Flexible interconnection for large EV charging depots

PG&E’s Flex Connect gives EV charging depots a day-ahead power limit, so they can connect and grow fleets before the grid is upgraded.

About this good practice

The US system operator PG&E offers a Flexible Service Connection, or Flex Connect, to customers with controllable power needs, such as EV chargers, so that they can connect to the grid without waiting for capacity upgrades. PG&E’s cloud-based Distributed Energy Resource Management System (DERMS), developed with Microsoft and Schneider Electric, coordinates a site’s demand according to when supply is readily available. It sends the site an hourly power limit forecast a day in advance so the customer can plan ahead.

The approach has been used at Tesla Supercharger sites in Santa Nella and Upper Lake, where a site that asks for 2 MW can draw the full amount most of the time and is limited to 0.5 MW only at peak times, such as hot summer evenings. At PepsiCo’s Fresno bottling facility, charging capacity rose from 3 MW at night and zero by day to up to 4.5 MW most of the time, allowing its electric semi-truck fleet to grow from about 30 to 50 trucks 18 months ahead of schedule. PG&E has expedited four sites so far, with more in development.

The programme complements regulatory measures introduces by the California Public Utilities Commission (CPUC). In September 2024, the CPUC established statewide electricity connection timelines for the three large investor-owned utilities. If met, these targets could reduce maximum connection times by up to 49 percent, with utilities required to report on delays every six months.