Using regulation to deliver anticipatory grid investment

Texas built 5,800 km of lines to remote wind zones ahead of generators, cutting wind curtailment from about 17% to 0.5% between 2009 and 2014.

About this good practice

In 2005 the Texas Legislature directed the state to plan for the transmission of wind power from remote areas to cities, and in 2008 the Public Utility Commission of Texas (PUCT), the state regulator, approved the Competitive Renewable Energy Zones (CREZ) plan. It identified resource-rich, high-wind zones in West Texas and the Texas Panhandle, far from the cities in Central and East Texas where most people live. The PUCT selected, through a competitive process, transmission companies or utilities to build lines to connect the CREZ with population centres. The project, completed in 2013, comprised about 5,800 km of high-voltage lines able to carry 18,500 MW and cost roughly USD 7 billion, recovered from all consumers. Building the grid for the zones, instead of waiting for generators to request connection one by one, allowed wind farms to connect and deliver power to the cities without delay: wind curtailment fell from about 17% in 2009 to about 0.5% in 2014. The lines can carry power from any source, and have also been used to connect gas generation. The lines later also carried a large, unplanned solar build-out. The programme is complete, and shows how regulation can permit anticipatory investment.