Procurement as an non-grid alternative to network reinforcement

Con Edison deferred a USD 1 billion substation by paying customers in Brooklyn and Queens for efficiency, demand response and storage.

About this good practice

The Brooklyn-Queens Demand Management programme, implemented by Con Edison and approved by the New York Public Service Commission in December 2014, is an early example of using location-specific procurement as an alternative to network reinforcement. Facing forecast overloads on sub-transmission feeders serving parts of Brooklyn and Queens, which would otherwise have required a new substation costing around USD 1 billion, Con Edison combined about 17 MW of traditional upgrades with about 52 MW of non-traditional, customer- and utility-side solutions. These included energy efficiency, demand response, distributed generation and battery storage, within a budget of about USD 200 million. Incentives were restricted to customers in the affected distribution networks. For example, a 2019 storage offering was paid USD 2,100/kW in exchange for the utility having the right for 10 years to dispatch the battery to relief the local distribution network. The programme deferred the substation need from 2017 to 2019 and was extended indefinitely in 2017, showing how geographically targeted flexibility can relieve network constraints.