Advanced reconductoring to substitute for new rights-of-way

The Netherlands and Belgium plan to reconductor most of their high-voltage backbone by 2035, adding capacity on existing towers without new rights-of-way.

About this good practice

The Netherlands and Belgium have decided to reconductor most of their high-voltage backbone by 2035, a strategy associated with their TSOs, TenneT and Elia. Reconductoring replaces existing conductors with advanced composite-core cables on the same towers and within the existing right-of-way. Research published in PNAS in 2024 finds that this approach can approximately double a line’s transmission capacity under suitable conditions, although actual gains depend on voltage support, line length and system stability, with a requirement for project-level studies.

Because the corridor is already in place, reconductoring avoids new land acquisition and much of the lengthy permitting that new lines require, with only limited additional permitting. New overhead lines in Europe and the United States often take more than ten years to build. The same study finds that total reconductoring costs are less than half those of new-build projects per unit length, even though advanced conductors cost two to four times more than conventional ones, because new structures and rights-of-way are avoided. According to the study, the two countries’ operators identified reconductoring as the fastest and most cost-effective way to support rapid renewable integration, reduce congestion and overcome difficulties in securing new rights-of-way. The case shows how upgrading existing corridors can substitute for building new ones, delivering capacity sooner and with less land impact. Outages still need careful scheduling, and some lines may need voltage support.

Read more about the good practice

Want to learn more about this best practice? Follow the links below.