About this good practice
The interruptible load programme allows RTE, the French TSO, to interrupt large industrial consumers’ electricity supply with less than five seconds’ notice to manage critical operating situations. It forms part of the Power System Defence Plan, which sets out remedial, last-resort and automatic measures to respond to disturbances that develop too quickly for human intervention. The interruptibility mechanism is the fifth category of defence measure. It enables RTE to reduce electricity demand by temporarily disconnecting participating industrial consumers before automatic load shedding is activated.
Two activation modes exist. All sites can be activated simultaneously and automatically on the basis of the supply–demand balance, or RTE’s dispatching can activate sites manually, one by one, according to local needs. Cumulated interruptible capacity must not exceed 1,200 MW.
Any aggregation of consumption sites connected to the public transmission or distribution grid is eligible, provided its contracted capacity exceeds 10 MW and its processes allow electricity consumption to be reduced below a specified power threshold within five seconds. Each year, RTE runs a call for tenders to select candidates for one-year contracts. Selected sites contract annually with RTE and are paid in exchange for making their consumption available for interruption. They also need technical approval: the site must meet the technical requirements, have telecommunication links with RTE and pass an actual interruption test. Sites contracted the previous year can be approved automatically if their performance record and ceiling power meet set conditions. The most recent call for tenders, for the period 1 January to 31 December 2026, contracted 16 high-voltage sites representing 1,135 MW. RTE monitors contractual availability in 30-minute intervals from measured consumption, so providers can track their own availability.
Read more about the good practice
Want to learn more about this best practice? Follow the links below.
- RTE. (n.d.). The interruptible load call for tenders. RTE Services Portal.