How the ISO/RTO model assign functions to each power system entity

US regional transmission organisations run the grid and wholesale markets independently of the utilities that own assets, with distinct, accountable roles.

About this good practice

PJM, MISO, CAISO and other regional transmission organisations (RTOs) have defined responsibilities for operating the electricity system, administering wholesale markets and coordinating transmission planning. As independent, non-profit organisations, they perform these functions separately from the utilities that own generation and network infrastructure. This model illustrates how distinct electricity-system functions can be assigned to dedicated, accountable organisations rather than managed entirely within vertically integrated utilities.

The model grew out of FERC Orders 888 and 889, which proposed the independent system operator (ISO) as one way for power pools to provide non-discriminatory transmission access. Order 2000 then encouraged voluntary RTOs and set out 12 characteristics and functions an entity must satisfy to qualify. ISOs and RTOs operate the grid independently of market participants, run bid-based energy and ancillary services markets that determine economic dispatch, and perform long-term planning. CAISO, for example, centrally dispatches generation, runs day-ahead and real-time markets, and operates an energy imbalance market extending across western states.

The contrast with other regions shows the value of the approach. In the Southeast and much of the West, vertically integrated utilities still handle operations, and physical power trade is largely bilateral. Yet two-thirds of the nation’s electricity load is now served in RTO regions. Variation persists, too: ERCOT operates an energy-only market under the Public Utility Commission of Texas.

Read more about the Good Practice

Want to learn more about this best practice? Follow the links below.