About this good practice
German TSOs are deploying large battery storage units, known as “grid boosters” (Netzbooster), at strategic grid nodes. Following the 2019 Network Development Plan, the regulator Bundesnetzagentur approved several pilot facilities. The largest, at 250 MW, is planned by TransnetBW at Kupferzell, with Fluence as supplier. Amprion is also developing a 250 MW decentralised grid booster in Bavarian Swabia, made up of five 50 MW battery modules and due to be operational from 1 January 2028. It is being developed in collaboration with E.ON and LEW Verteilnetz, with EDF power solutions Deutschland awarded the contract to build and operate the plant.
Grid boosters act as a rapid-response safety buffer. Lines are normally kept partly unused as a reserve for the (n-1) case, when another line fails. When a fault occurs, a controllable load on the generation side of the bottleneck absorbs power that cannot be transported, while a battery on the consumer side supplies consumers within seconds, bridging the gap until conventional power stations take over. This lets operators use part of the reserve to carry electricity in normal operation. Operators can therefore reduce the costly preventive redispatch that is needed when northern wind power overloads lines towards southern demand centres.
Grid boosters do not replace grid expansion beyond 2030, but they can defer or reduce the need for new lines, which cost more, take longer and have a larger footprint. If the pilots succeed, other solutions, such as distributed storage or flexible loads, may follow. Amprion’s project also stands out for its multiple uses: it can relieve the regional distribution grid and sell on the electricity market when not needed for the transmission grid.
Read more about the good practice
Want to learn more about this best practice? Follow the links below.
- https://www.energy-storage.news/fluence-building-250mw-grid-booster-battery-storage-system-for-german-tso-transnetbw/
- https://www.transnetbw.de/en/company/portrait/innovations/grid-booster
- https://energiewende.bundeswirtschaftsministerium.de/EWD/Redaktion/EN/Newsletter/2020/02/Meldung/direkt-account.html
- https://www.amprion.net/Press/Press-Detail-Page_88640.html