About this good practice
The NOVA principle prescribes that the grid needs to be optimised before it is reinforced, and reinforced before new lines are built. German transmission grid expansion planning is generally required to follow this principle. The requirements are anchored in law and the TSOs apply them in the Network Development Plan before the market simulation is conducted. New lines are only proposed where cheaper options using existing assets cannot meet the need. This ensures that expansion is limited to what is needed, which keeps costs down and reduces local opposition.
Read more about the good practice
Want to learn more about this best practice? Follow the links below.