Using multi-year price controls to provide predictable returns for grid companies and investor certainty

Ofgem sets network revenues for five years, including a return on capital, so investors know what to expect when financing large grid investments.

About this good practice

In Great Britain, the energy regulator Ofgem sets how much revenue each network company, the owners of the electricity and gas grids, may earn, using multi-year price controls called RIIO (Revenue = Incentives + Innovation + Outputs). The allowed revenue includes a return on the capital the company invests. Because returns and revenues are fixed for a five-year period, investors know what to expect, which supports financing of large grid investment. For RIIO-3 (April 2026–March 2031), Ofgem approved an initial GBP 10.3 billion for electricity transmission, with total expected spending potentially rising to GBP 70 billion. RIIO-3 is in force. By giving network companies predictable returns, it contributes to ensuring adequate and predictable returns for grid companies.