Digitalise connections and permitting processes end to end 

Digitalising connection and permitting end to end on one platform, with digital twins auto-approving standard low-risk applications, reduces delays.

About this measure

Digitalise connection and permitting processes through integrated platforms that support application submission, processing and tracking and stakeholder engagement across the full project lifecycle. Where feasible, these platforms should operate as one-stop shops, bringing together permitting and grid connection procedures within a single interface to reduce administrative complexity, improve coordination between authorities and grid operators, and provide real-time transparency for applicants. 

Advanced digital tools, including digital-twin-based systems, can further streamline connection management by automatically assessing standard applications against current grid conditions, technical constraints and available hosting capacity. This enables rapid rules-based approval of low-risk and standardised projects while reserving human engineering expertise for complex or high-impact cases. Together, these tools can reduce delays, improve consistency and create a more efficient and predictable pathway for electricity infrastructure development and grid access. 

Core recommendation for this measure

Deploy

4.2 Streamline connection management


Connection timelines are one of the main constraints on renewable deployment and electrification,…

Related recommendations

Deploy

3.1 Streamline permitting


Administrative and permitting procedures, not construction, tend to account for the majority of the…