Why this objective matters
New sources of power supply and demand can typically be built in months or a few years, but connecting them to the grid routinely takes far longer. As such, grid connection is increasingly a bottleneck for economic growth, and for renewable deployment and electrification. Solar, wind and storage dominate connection queues, while EV charging, heat pumps, industrial electrification and data centres add large and/or fast-growing loads. Procedures, queues and technical requirements built for a smaller number of large, predictable connections now produce long waiting times, opaque queues and inconsistent requirements that create uncertainty for investors and end users. The terms of access are equally rigid, since most systems still grant round the clock, or “firm”, worst-case connection rights and apply uniform requirements regardless of how much a project affects the grid.
Current connection practices leave existing capacity underused while projects wait for reinforcement that may not be needed. Entry to a connection queue is usually cheap and carries little obligation. This leads to queues filling with speculative and stalled projects that hold capacity they may never use while viable projects wait behind them. Firm access terms mean that every project secures the maximum network capacity it might ever need and capacity is reserved for conditions that rarely arise.
The technical rules, meanwhile, have not kept pace with the nature of what is connecting: the equipment arriving at scale is increasingly inverter-based, distributed and interconnected. Where interoperability standards and grid codes are unclear or fragmented, assets are deployed in a way that impedes their coordination, can degrade power quality and at high volumes can put system stability at risk. Because such rules shape an entire stock of equipment, those set late must be retrofitted to assets already installed, at far greater cost than specifying them from the start.
Getting connection wrong is costly, with impacts compounding over time. When a transition-compliant asset cannot connect within the window its investment case allows, firms reinvest in fossil-fuelled equipment because the electrified alternative cannot be connected in time, locking in carbon and import dependence for the life of that asset. At the same time, clean generation waits in queues for new and electrified demand that materialises late. Equipment connected without adequate technical rules surfaces later as a stress on the system rather than a resource. Getting it right turns the same moment to advantage: assets that connect quickly, arrive capable of supporting the system and are rewarded for operating flexibly make fuller use of the grid already built and leave the system with more flexibility to draw on in operation.
What’s at stake
Security
Equipment standards and grid codes determine how effectively the many assets now connecting can be integrated. Set early, they build a fleet of equipment that can be coordinated and respond to system conditions, allowing a system to integrate local supply and operate reliably with a higher share of inverter-based assets.
Competitiveness
Faster, proportionate connection processes and flexible connection terms let willing projects connect sooner, while a slow, rigid regime pushes investment elsewhere and drives firms that cannot connect in time back towards fossil-fuelled equipment for another asset cycle.
Affordability
Rigid, worst-case connection terms reserve capacity for conditions that rarely occur, leaving headroom unused while driving up investment in grid reinforcement. Proportionate processes, flexible terms and timely standards all reduce the costs that would otherwise have to be recovered from consumers.
What this objective calls for
A faster and more capable interface is needed between the grid and the supply and demand connecting to it. This can be delivered through three connected reforms that together determine what connecting assets and projects must be able to do, how quickly they can be processed and on what terms they are granted access. The reforms should:
1. Set standards and grid codes. The technical rules that connecting equipment and projects must meet should be established as soon as possible. This covers the interoperability standards that allow devices from many vendors to exchange information and be coordinated, and the grid codes that define how assets behave. Requirements should be tiered according to the size of the project and where in the grid it connects, with a compliance regime that verifies and enforces them, and a review process that keeps them current.
2. Streamline connection management. Connection processes should be faster, more transparent and proportionate. This requires setting minimum requirements for applicants, clearing queues of non-viable projects, requiring digitalised submission and assessment, publishing network hosting capacity, conducting more efficient tiered and batched grid connection studies, ensuring coordination between transmission and distribution systems, and setting binding timelines backed by accountability.
3. Reward flexibility with better connection terms. Access terms should reflect what a connecting party is prepared to accept and do. Projects willing to be curtailed, to connect in phases, to share a connection point, to site where capacity exists, to operate within limits that vary with system conditions or to offer other flexibility and system services should receive faster and cheaper access in return, so that existing headroom is utilised more fully.