Establish overriding public interest provisions for grid expansion

Presuming that grid projects serve the public interest shifts the burden towards justifying refusal, without exempting them from environmental review.

About this measure

Establish in law that grid infrastructure, and where appropriate other infrastructure critical to the energy transition, is presumed to serve an overriding public interest in the balancing of interests within environmental and planning assessments. The designation does not exempt projects from environmental review or override other obligations; it ensures the public interest in energy security, decarbonisation and affordable electrification is given due weight, and shifts the burden of justification towards demonstrating why a project should be refused. It belongs in Stage 3 because its legitimacy is conditional on the procedural safeguards being in place first (e.g. the mandated early engagement, proportionate tiering and dispute resolution mechanism), as well as the stronger, more integrated planning methodologies being realised. To preserve public trust it must not become a blanket override; clear qualifying criteria, robust mitigation measures and compensation where impacts are unavoidable are essential, as is transparency about how the balancing of interests is applied.

Core recommendation for this measure

Deploy

3.1 Streamline permitting


Administrative and permitting procedures, not construction, tend to account for the majority of the…

Related recommendations

Enable

9.1 Involve stakeholders


Decisions that affect communities and electricity users are multiplying across grid planning,…

Enable

9.2 Fairly distribute burdens 


Grid modernisation creates burdens through infrastructure deployment, cost recovery mechanisms and…