3. Accelerate grid deployment

Even well-planned grids can stall during delivery. Permitting alone can take the better part of a decade, financing has become a binding constraint in many systems, and lead times and prices for key equipment have increased sharply in much of the world. When grid deployment lags, clean supply and new demand are forced wait to connect, costs rise and the grid holds back the wider economy. Faster permitting, better access to capital and more resilient supply chains ensure that approved grid investment is deployed on time.

Why this objective matters

In many jurisdictions deciding what to build is no longer the binding constraint on grid expansion; building it is. The outcomes of objectives 1 and 2 – planning reform and integrated planning – improve the system of determining what should be built and where. The challenge of interest here is getting it built, on time. The length of time needed to plan, permit and build major grid infrastructure can reach a decade or more, and administrative procedures rather than physical construction account for most of it. As electrification increases demand and variable renewables expand, the gap between the grid capacity that is needed and the capacity that can be delivered is widening.

There are three central bottlenecks: permitting and wider administrative procedures, constrained access to capital, and equipment supply chains. Each can slow projects on its own, and together they compound the delays: a project held up in permitting ties up scarce capital and a manufacturing slot, while weak balance sheets delay the orders manufacturers need before they can expand capacity.

Lead times and prices for key equipment such as cables and transformers have risen sharply, and supply is concentrated among a small number of top-tier manufacturers, which bears hardest on smaller buyers and on emerging and developing economies.

The consequences of inaction compound over time. When deployment cannot keep pace, the result is connection queues, curtailment of clean generation, deferred electrification and power system reliability risks, alongside higher costs as delay inflates financing and forces projects to be redesigned. Electrification projects that cannot connect stall, and fossil-fuelled alternatives are locked in for another asset cycle. Addressing these constraints turns credible plans and committed capital into operational grid capacity, and how quickly it is done increasingly determines how fast the wider transition and new electricity-intensive economic activity can proceed.

What’s at stake

Security

Competitiveness

Affordability

What this objective calls for

This objective calls for action on three constraints: permitting, access to capital, and supply chains. Together the recommendations accelerate grid deployment, and the three reforms are designed to be pursued in parallel:

1. Streamline permitting. Permitting and administrative processes should be made faster, more predictable and proportionate to project scale, without weakening environmental and social safeguards. Where possible, reform should simultaneously cover permitting for grid, supply, storage and demand infrastructure rather than pursuing them on separate tracks, given that the same authorities typically handle all of them.

2. Improve access to capital. The financial health and creditworthiness of grid companies should be strengthened and a wider range of capital mobilised. Predictable regulated returns and stronger balance sheets, complemented by green, blended and development finance, can ease the financing bottleneck.

3. Strengthen supply chains. Supply chains for critical equipment and materials should be made resilient and diversified. Transparent long-term demand signals, standardisation, coordinated procurement and larger inventories improve the availability of transformers, cables and other components.

Policy recommendations

Deploy

3.1 Streamline permitting


Administrative and permitting procedures, not construction, tend to account for the majority of the…

Deploy

3.2 Improve access to capital


Grid deployment is increasingly limited by access to affordable capital, often because grid…

Deploy

3.3 Strengthen supply chains


Lead times and prices for key pieces of grid equipment have risen sharply, constraining deployment.…