About this measure
Phased connection agreements allow applicants to secure grid capacity progressively in line with planned project development and future electricity demand. Develop a framework that allows applicants to specify staged access needs over defined time horizons, for example increasing capacity as industrial electrification, production expansion or supporting infrastructure comes online. This approach provides greater planning certainty for both grid operators and project developers, enabling grid investment and reinforcement decisions to better reflect expected demand growth. Phased agreements can also reduce over-procurement of connection capacity, improve utilisation of existing infrastructure and support more coordinated long-term grid planning. Unlike flexible connection agreements, which manage operational constraints from day one, phased agreements focus primarily on the timing and sequencing of capacity delivery.