Why this recommendation matters
There is a structural mismatch between the speed of grid expansion and the speed at which the energy system around it evolves. Where grid investment can only follow confirmed need for grid infrastructure, power supply and demand projects stall even when the policy direction is clear. Prolonged connection timelines can undermine the bankability of new supply and demand projects. Where reinvestment cycles arrive before the grid is ready to accommodate additional demand, industrial and commercial users might also commit to fossil-fuelled equipment for another cycle, locking in avoidable carbon emissions.
Anticipatory investment addresses this by allowing investment ahead of time where future need is credible and well evidenced. Forecast-based reinforcement, staged investment and risk-sharing mechanisms such as guarantees or backstop recovery tools make proactive buildout viable.
Done well, this approach reduces connection queues, avoids expensive stop-start development and gives demand growth, renewable connections and distributed energy resources the grid bandwidth to come online. Because building ahead places capital at risk before need is confirmed, the terms on which its costs and risks are shared determine whether it happens at all, and whether those costs fall fairly.
Several barriers hold anticipatory investment back. Financing for new grid infrastructure typically requires short-term demand certainty that is incompatible with asset reinvestment cycles of 15 to 20 years. Grid planning cost–benefit analyses rarely include carbon abatement or other wider system benefits as criteria, since grid companies and regulators are not directly exposed to carbon costs. Grid companies face debt constraints and an absence of long-term investment rules. And because grid costs fall on consumers who may not be the principal beneficiaries of the capacity being built, cost allocation has to be handled with care.
How to act on this recommendation
Stage 1
Policymakers should establish governance that makes anticipatory investment credible to avoid grid investment routinely running ahead of need.
Prioritise independent review and approval of grid investment plans so that investment needs are assessed transparently, consistently and against system-wide objectives. This scrutiny depends on the planning methodologies in recommendation 1.1 and on the governance provisions of objective 7, and it builds the public trust that proactive investment will later require.
Stage 2
Regulators should define when anticipatory investment is justified, how it is targeted, and how its costs and risks are shared.
Reward investment in assets that offer higher utilisation and higher system value, and reform rules that require short-term demand certainty so that anticipatory investment is permitted and treated as a regulated asset under clear eligibility criteria drawn from scenarios, connection pipelines, policy targets and spatial plans. Furthermore, design a system for recovering anticipatory costs, placing an appropriate share on future connecting users rather than today’s consumers alone, phasing recovery in line with utilisation, and drawing on public budgets where wider public benefit justifies it. Scenario-based prioritisation should target grid reinforcement where it is most needed and be published for scrutiny. And risk-sharing mechanisms should spread the cost of any underutilisation across grid companies, developers, consumers and, where appropriate, public budgets. These measures connect strongly to the scenario-based planning in recommendation 1.1 and to improving access to capital under recommendation 3.2.
Core measures
Implementation considerations
Anticipatory investment realigns interests in ways that need active management. Grid companies and project developers generally welcome it, since it removes a barrier to connection and may expand the regulated asset base. Regulators, consumer advocates and finance ministries are more cautious, because building ahead of proven need places capital at risk and can raise bills before the benefits materialise. Investors require predictable and durable cost recovery rules before committing to long-lived assets. The central point of contention is the allocation of underutilisation risk and the credibility of the evidence used to justify investment. Clear eligibility criteria, transparent scenarios and well-defined risk-sharing arrangements are what allow these interests to be reconciled.
The equity dimension is significant because grid costs are ultimately recovered from consumers. Building ahead of need can mean that today’s consumers, including vulnerable households, contribute to capacity whose principal beneficiaries are future large energy users or project developers. Cost recovery design should reflect this, for example by recovering an appropriate share from future connecting users and, where justified by wider public benefit, from public budgets. There is also a spatial dimension: anticipatory investment tends to flow to areas of expected high growth, which can deepen regional disparities unless planning deliberately weighs access and balanced development. Tying anticipatory investment to credible evidence, fair cost allocation and explicit attention to who benefits is key to safeguarding both efficiency and equity.