About this measure
Map the existing permitting and administrative pathways for power system infrastructure, and identify where delays are incurred. A structured audit maps the agencies involved, the sequence and duration of each step, the points where applications stall, and whether the binding constraint is the rules themselves or the under-resourcing of the bodies that apply them. The diagnostic is fast and low cost, and logically precedes the rest of the recommendation: it tells policymakers where to improve coordination, how to set the tiers and criteria for differentiated pathways (e.g. for project size or complexity), where binding timelines might be challenging to meet, and which steps to digitalise first. Publishing the findings builds the case for reform and creates a baseline against which later progress can be tracked.