Why this recommendation matters
Supply-chain constraints in the supply of critical grid equipment are slowing deployment. According to the IEA, average lead times for power cables and large transformers have almost doubled since 2021, reaching two to three years for cables and up to four years for large power transformers, with lead times for high-voltage direct-current cables exceeding five years. Prices have risen in step: in real terms, cable costs have nearly doubled since 2019 and power transformer prices have increased by around 75 percent, with underlying materials such as copper, aluminium and grain-oriented electrical steel also more expensive. This reflects a market in which supply is concentrated among a small number of top-tier manufacturers, which has the greatest impact on emerging and developing economies that have less purchasing power and face longer queues.
Supply chains should be diversified and made more resilient. Publish transparent, long-term project and investment pipelines to give manufacturers the demand certainty they need to expand capacity.
Harmonising and standardising equipment specifications should broaden the supplier base, while coordinating or pooling procurement allows it to gain efficient scale and negotiating power. Long-term framework contracts can be used to tie guaranteed volumes to manufacturer capacity commitments. Focus on holding strategic reserves of critical components with long lead times, actively diversifying the supplier base, and keeping materials in use through circular-economy approaches.
Resilient supply chains enable more reliable, cost-effective grid deployment. Shorter, more reliable equipment lead times mean that projects can proceed as soon as they are permitted and financed. Diversified supply and strategic reserves reduce the risk that a disruption, disaster or geopolitical shock leaves critical components unavailable. A broader, more competitive supplier base and standardisation could put downward pressure on prices. Acting early is important as capacity expansion, standardisation and workforce development all take years to bear fruit.
How to act on this recommendation
Stage 1
Improve the ability of manufacturers and suppliers to see and anticipate future demand for equipment and build the foundations for future capacity to deliver.
Policymakers and grid companies should publish transparent, long-term project and investment pipelines grounded in scenario-based planning, and begin harmonising and standardising equipment specifications, adopting international standards where they exist and are relevant. Workforce development, addressed in recommendation 8.3, is also a Stage 1 priority, since training pipelines lasting several years must precede peak deployment. Pipeline visibility depends on the planning outputs of recommendation 1.1 and gains credibility from the anticipatory investment frameworks of recommendation 1.2 and the multi-year revenue certainty of recommendation 3.2.
Stage 2
Convert demand signals into manufacturing capacity, and broaden the equipment supply base.
As equipment requirements ramp up, policymakers should enable grid companies to coordinate or pool procurement to achieve more efficient scale and stronger negotiating power. This is particularly relevant for smaller grid companies. Grid companies should enter long-term framework contracts that link guaranteed demand volumes to manufacturer capacity commitments, and actively diversify and develop the supplier base, qualifying second-tier and local suppliers and building in dual sourcing to avoid single points of failure. Framework contracts are made possible by the regulatory authorisation and revenue certainty of recommendation 3.2 and on the standardisation of Stage 1.
Stage 3
Maintain resilience as the equipment mix evolves.
Policymakers should establish strategic stockpiles and spare-sharing arrangements for critical components with long lead times, such as large transformers. They should also advance circular-economy and material-efficiency approaches, including recycling, refurbishment, design for recyclability and sustainable materials, to ease primary material demand. Optimising existing assets through reconductoring, applying grid-enhancing technologies and extending lifetimes also reduces demand for new equipment and is addressed under recommendation 1.3 and objective 5. Building strategic reserves depends on the standardisation of specifications to ensure spares are interchangeable, and on regulatory treatment that allows stockpiling costs in the regulated asset base.
Core measures
Implementation considerations
Supply-chain policy sits at the meeting point of energy, industrial and trade policy, and interests tend to diverge along those lines. Grid companies want equipment supply certainty and competitive prices; manufacturers want demand visibility, adequate margins and protection from low-cost competitors; policymakers weigh deployment speed against industrial-policy goals such as domestic jobs and strategic autonomy; and workers have a stake in training and the location of manufacturing. A central tension is between resilience and cost efficiency: long-term framework contracts and strategic equipment reserves provide insurance against disruption, but may lock in prices above short-term competitive procurement; and while domestic manufacturing requirements may reduce import dependence, they can raise costs if local production is less efficient. Policymakers should be explicit about these trade-offs and design measures, such as dual sourcing, that reduce concentration risk while preserving competition.
Emerging and developing economies often face supply-chain disadvantages. They have less purchasing power to secure scarce equipment, less domestic manufacturing capacity, and longer delivery queues as suppliers prioritise larger, higher-margin markets. Procurement pooling, advance procurement backed by development finance and technology-transfer arrangements can help redress this imbalance. The geography of new manufacturing investment also matters for a just transition: if capacity expansion is confined to advanced economies and a few large producers, the associated jobs and economic development will bypass the regions that most need them. Carefully calibrated local-content requirements and targeted workforce development can help avoid such outcomes.