Adopt curative congestion management

Higher flows are allowed before a fault because a fast automatic remedy, such as an intertrip scheme or storage, acts after it, instead of holding capacity in reserve.

About this measure

Enable a shift from preventive to curative management of grid constraints. Under curative management approaches, higher flows are permitted before a fault because a fast, reliable automatic remedy acts after it, within the timeframe under which the equipment tolerates the overload. Conventional practice is preventive, constraining flows so the system survives the worst credible contingency without further action, which holds capacity in reserve against an event that usually does not occur. Two instruments deliver this: first, special protection and intertrip schemes disconnect or rapidly de-load designated generation on a defined fault, so the post-fault overload never materialises. The constraint management intertrips used in Britain on its most congested boundaries allow operation beyond the planned stability limit on this basis. Second, storage operated as a grid asset achieves the same end by absorbing or injecting power at strategic points until slower measures take effect. For example, Germany’s grid boosters are sized to sustain roughly an hour, long enough to redispatch, and were approved under the proviso that they cost no more than the congestion relief they deliver. Implementation requires rigorous testing, since the higher pre-fault flow depends on the scheme’s reliability, clear accountability for operation and failure to operate, and regulatory treatment that allows operators to hold or contract the capability and recover its cost. The ability to use storage as a grid asset depends on the institutional context, since grid operators are often prohibited from owning generation-like assets.

Core recommendation for this measure

Operate

5.3 Optimise the use of existing infrastructure


Grid assets and contracted generation are routinely operated below their safe technical capability,…

Related recommendations

Plan

1.3 Leverage alternatives to reinforcement


Systematically evaluating alternatives reduces reliance on conventional grid expansion. Options…