About this measure
Define how the costs of grid upgrades triggered by new connections are allocated: between the connecting party and the wider base of grid users, among multiple projects in the same cluster that share a reinforcement, and over time as later projects benefit from upgrades that earlier ones funded. These rules should be transparent, predictable and set under regulatory oversight rather than through bilateral negotiation, since they determine what a connecting party pays and form the basis on which any reward for flexibility is calculated. The choice between shallow charging, where the connecting party pays only for its direct connection, and deep charging, where it also bears a share of wider reinforcement, should be settled explicitly as a jurisdictional policy decision, since the choice shapes both who pays and where projects choose to locate.