About this measure
Establish legally binding maximum connection timelines, backed by accountability mechanisms such as penalties for grid companies that consistently miss the timeline, deemed-approval provisions where the responsible utility fails to respond within the limit, and formal redress procedures for applicants. Binding timelines are the endpoint of connection reform rather than its starting point because they only work once the process, resourcing and digital tools behind them can deliver, and once the institution charged with administering the regime has the capability to do so credibly. Set too early, they move the bottleneck rather than removing it.