About this measure
Put a mechanism in place to coordinate the agencies involved in permitting power system infrastructure, so that environmental, technical and administrative assessments run in parallel rather than in sequence, with clear ownership of decision timelines. Coordination can be delivered along a spectrum, from a designated lead authority that coordinates the permitting process while each agency keeps its own decision-making, through to joint review procedures and shared schedules. Its effectiveness depends on it being set out in legislation or regulation rather than informal arrangements, on conferring real authority (objective 7) and on adequate resourcing (objective 8). Coordination is the foundation that a single point of contact (measure Establish a single point of contact) later builds on, and is well supported by the digital permitting platform in measure Develop an integrated digital permitting platform.