3.1 Streamline permitting

Administrative and permitting procedures, not construction, tend to account for the majority of the time it takes to deploy grid infrastructure. Permitting has to be made faster, more predictable and proportionate to project scale, while keeping environmental and social safeguards intact. Faster permitting brings clean supply and new demand online sooner and lowers or avoids the cost of delay. Reforms work best when designed once to cover grid, generation, storage and demand infrastructure together. The introduction of binding timelines for permitting can only deliver if permitting authorities are adequately resourced.

Why this recommendation matters

Administrative and permitting processes are among the largest controllable sources of delay in grid deployment. In many jurisdictions the time needed to plan, permit and build a major transmission line can exceed a decade, and administrative procedures rather than physical construction account for most of that period. Distribution-level projects face less extreme but still material delays where local permitting is fragmented or under-resourced. As electrification increases demand and variable renewables expand, the gap between the grid capacity that is needed and the capacity that can be delivered is widening.

Permitting and administrative processes should be streamlined and standardised by making safeguards more efficient and proportionate. Policymakers have to work to reduce duplication across agencies and tiers of government, set clear timelines and responsibilities for permitting authorities, allow parallel rather than sequential approvals, and create differentiated pathways for projects of different complexity and expected impact. There is a strong case for designing and implementing reform once to cover power grid, supply, storage and demand infrastructure together, since the same environmental, planning and land-use authorities typically handle all of them and separate reform processes may duplicate effort and prevent streamlining.

Faster permitting has cross-cutting benefits. It brings forward the connection of clean power supply and new demand, both because grid capacity becomes available sooner and because non-grid projects can clear administrative procedures faster, which keeps electrification and new economic activity on schedule. It lowers cost, since protracted permitting raises financing costs, deters investment and forces the redesign of projects overtaken by changing conditions. And it supports system security by allowing grid deployment to keep pace with supply and demand, avoiding the congestion, curtailment and reliability risks that follow when the grid falls behind. Streamlined permitting also strengthens the credibility of the anticipatory investment facilitated by recommendation 1.2, since investors and regulators commit ahead of need more readily when projects can be delivered on schedule. Well-designed reform can raise public trust, including through early, structured engagement, which also consistently reduces later legal challenges.

How to act on this recommendation

Core measures

Implementation considerations

Streamlining requires balancing several legitimate interests. Grid utilities and developers benefit from faster processes and tend to support them, while environmental organisations and affected communities may fear that efficiency comes at the expense of safeguards and participation. That concern is well-founded where reforms are poorly designed. Policymakers face pressure from both sides, and local government may resist losing decision-making authority over infrastructure seen as serving national goals at local cost. These tensions are manageable with deliberate design: streamlining should target procedural inefficiency, such as duplication, sequential processing, unclear responsibilities and under-resourcing, rather than substantive protections. Differentiating pathways according to project magnitude keeps scrutiny high for high-impact projects while lifting disproportionate burdens from more routine ones, and binding timelines should come with genuine resourcing.

Communities with less political voice or institutional capacity are the most exposed. They may bear the burden of siting decisions when processes are accelerated without adequate consultation, yet they also suffer most from delayed grid modernisation when ageing infrastructure and poor reliability persist in underserved areas. Reforms should therefore ensure that acceleration does not systematically disadvantage particular communities. Achieve this by, for instance, retaining minimum consultation requirements within fast-track procedures and by weighing distributional impacts explicitly when corridors and zones are designated.