Why this recommendation matters
In many systems the methods used to determine the amount, location and timing of grid capacity were designed for a different era. They still extrapolate demand from historical trends, take decisions about centralised generation as their starting point, treat transmission and distribution as separate exercises, and assess investments mainly against criteria for peak capacity and adequacy. As renewables, distributed energy resources and electrified demand grow, these methods misjudge the system in predictable ways. They understate the need for flexibility, overlook how distribution-level resources change transmission needs, and fail to anticipate the voltage, frequency and stability challenges that arise as inverter-based resources displace synchronous generation.
Each of these planning failures negatively affects cost and reliability. Plans built on a single forecast fail to manage the uncertainty of the timing and location of new renewables and demand. An appraisal that counts only near-term financial return understates the value of infrastructure that would unlock electrification, meaning that projects with wider system benefits are deprioritised.
Planning that cannot see distribution-level resources or large incoming loads misses both the constraints they create and the services they could provide. The result is a grid that is over-dimensioned in some places and under-dimensioned in others, with the costs and reliability impacts of both ultimately falling on consumers.
Modernised planning methodologies improve the quality of decisions. Scenario-based planning identifies the investments that hold their value across a range of futures. Integrated transmission and distribution planning reveals where distributed energy resources allow reinforcement to be deferred. Explicit assessment of flexibility, stability and resilience brings into the plan the system properties that determine whether a grid with a high share of renewables, distributed energy resources and electrified demand can operate reliably and cost-effectively.
How to act on this recommendation
Stage 1
Policymakers should establish the regulatory foundations for modern planning.
This means adopting scenario-based planning for grid development plans, built from a minimum set of distinct, plausible scenarios with transparent assumptions that are updated regularly. In addition, reform investment appraisal to ensure it values wider system benefits. Establish foundational data sharing between the transmission and distribution level, including operators, network companies and market participants, and require large-load projects – from data centres to industrial and transport electrification projects – to share sufficient data to inform planning. Planners should also perform resilience screening for new infrastructure. This work is tied to the capacity-building in objective 9 and the transparency provisions of objective 7 as regulators must be equipped to commission and interrogate more complex modelling.
Stage 2
Policymakers should require the operationalisation of modern planning methodologies and full integration of transmission and distribution systems into planning.
Require planning to assess flexibility, both to accurately assess system needs and accurately value the services from resources such as storage and flexible demand resources. Resilience should also move from a screening step to a deeper, metrics-based analysis. Strengthening coordination between transmission and distribution planning allows investment decisions to reflect distribution-level developments that will increasingly drive transmission needs. This stage has strong interdependencies with the policies on modernising grid codes and upgrading connection management in objective 4. Enhanced data transparency and modelling capabilities become critical to support more sophisticated system analysis.
Stage 3
System planners should adopt the analytical methods that a system with a high share of renewables and distributed energy systems requires.
Probabilistic adequacy and reliability metrics should replace deterministic standards, so that reliability is assessed against the likelihood and cost of shortfall rather than a fixed margin. Bring stability assessment and system restoration planning into grid development plans for systems with a high share of inverter-based resources, and introduce common planning data standards and minimum data quality requirements at the latest here. At this stage planning becomes closely linked with the operational capabilities of objectives 5 and 6: planning can only reliably count on operational practices that have been proven to work.
Core measures
What to consider during implementation
Modernising planning methodologies generally aligns with the interests of system operators, renewable developers and electricity users since it improves the visibility of future grid capacity and reduces uncertainty around expansion and connection opportunities. Tensions typically arise around investment timing and cost allocation, and regulators and consumer groups may be concerned about cost increases. Closer coordination between transmission and distribution planning may also require adjustments to established roles, data-sharing practices and investment responsibilities between operators. Transparent methodologies, open data and structured stakeholder consultation are therefore essential to build trust in scenario assumptions and investment decisions.
Equity considerations arise around how investments and related costs are allocated. Scenario-based planning may prioritise investment in regions with faster renewables deployment or stronger demand growth, which can widen geographic disparities. Policymakers should ensure that planning scenarios reflect diverse regional development pathways, including areas with slower economic growth or lower electrification potential. Cost allocation frameworks should be designed so that investments required for the energy transition do not disproportionately increase costs for vulnerable consumers. Transparency, inclusive consultation and balanced cost recovery help ensure that modern planning frameworks support both efficient grid expansion and equitable outcomes.