How to Use

Challenge brief: integrating data centres

About the challenge briefs. Each challenge brief takes a problem that many power systems face and brings together the parts of the toolkit that help address it. The relevant recommendations and measures come from several objectives, since most challenges cut across planning, deployment, operation and the enabling environment. Use the brief as a route into the toolkit, then follow the links to the recommendations and measures for the full detail. 

The challenge

Data centres bring very large demand at high speed. A single facility can require hundreds of megawatts, and developers typically want power within one to three years. Grids are rarely planned for loads of this size in the locations where they appear, and new high-voltage connections, grid reinforcement and conventional generation typically take five to ten years. Supply chain constraints on transformers, cables and gas turbines lengthen these timelines further. In many cases the binding constraint is access to the grid itself, even where enough supply could be made available. 

Part of the demand is speculative. Because developers know that connecting large loads is difficult, they often submit requests in several locations at once. Grid planners then face the risk of investing for demand that never materialises, or of delaying projects that are real. 

Data centres can also behave in ways the grid is not used to. Their demand is largely served through power electronics. Without suitable technical requirements, a minor disturbance on the grid can lead a facility to switch to its backup supply, causing large, sudden changes in demand within seconds or less. As more and larger facilities connect, these changes become a challenge for system stability. 

Integration can put pressure on affordability. Accommodating data centres can require significant investment in the grid and in supply. How these costs are allocated, and whether the cheapest available solutions are chosen, determines whether other grid users pay more. It also shapes how host communities view new facilities, and with it the social licence for further development. 

How the toolkit helps

The toolkit points to five principles for action, grouped under the three parts of the challenge.

Making room for new demand

Plan for demand that is likely to materialise. Requiring developers of large loads to share their plans with grid planners at an early stage, and setting minimum requirements for connection applications, such as evidence of site control and a financial commitment, help separate serious projects from speculative ones. Mapping the energy needs of economic development and designating zones for large loads let planners prepare the grid where demand is expected, and invest ahead of need where the case is well evidenced. Draws on recommendations 1.1 modernise planning methodologies, 1.2 enable anticipatory investment, 2.1 integrate with transition planning, and 4.2 streamline connection management. 

Connect faster in return for flexibility. Data centres can often reduce or shift a small share of their demand, for example during a limited number of hours a year when the grid is most constrained. Connection terms can offer faster access in exchange for binding flexibility commitments, such as accepting curtailment during scarcity, installing on-site storage, or connecting in phases as grid capacity becomes available. Published hosting capacity and locational signals in connection charges can steer facilities towards parts of the grid with room to spare. Draws on recommendations 4.2 streamline connection management, and 4.3 reward flexibility with better connection terms. 

Create grid capacity with solutions that can be deployed quickly. Where the grid or supply cannot be expanded on a data centre’s timeline, options that can be deployed in months to a few years become important: battery storage at utility scale and in homes and businesses, solar and wind where possible, grid-enhancing technologies, reconductoring, and the activation of demand-side flexibility from other grid users. Data centre developers can be allowed to meet part of their obligations by funding such solutions on the local grid. Draws on recommendations 1.3 leverage alternatives to reinforcement, 5.3 optimise the use of existing infrastructure, 6.1 broaden participation, and 6.2 coordinate power flows with prices, tariffs and programmes. 

Keeping the system stable 

Set clear technical requirements for large loads. Grid codes and connection agreements increasingly treat large loads much as they treat large generators. Requirements can cover riding through grid disturbances without disconnecting, maximum ramp rates, visibility and controllability for the system operator, power quality and data provision. Setting these rules before large volumes connect costs less than correcting behaviour afterwards. Draws on recommendations 4.1 set standards and grid codes, and 5.1 operate the bulk system flexibly and securely. 

Sharing the costs fairly

Keep integration cost-effective and share costs and benefits transparently. Transparent methodologies for allocating connection and grid costs show host communities and other grid users who pays for what, and recover an appropriate share from the facilities that drive the investment. Grid companies should be required and rewarded to choose the most cost-effective integration options, for example a connection that can be curtailed for a few hours a year in place of reinforcement sized for the facility’s peak demand. Where data centres fund batteries or other flexible resources for nearby households and businesses, these can help make room for the facility on the grid at times of stress and lower participants’ bills at other times. Draws on recommendations 4.3 reward flexibility with better connection terms, 7.2 revise grid company governance, 9.2 fairly distribute burdens, and 9.3 enable benefit participation. 

Where to start

The measures below are examples of where action on data centre integration typically begins, placed by domain and by stage of grid modernisation. The number after each measure is the recommendation it belongs to. Finding your starting point explains how to identify your system’s stage, and develop a reform roadmap explains how to sequence measures from there. 

Stage 1: Foundation Stage 2: Acceleration Stage 3: Transformation 
Plan Mandate large-load data sharing (1.1) 
Build utility and regulator capability to identify and evaluate alternatives (1.3) 
Identify the energy and infrastructure needs of economic development (2.2) 
Recover anticipatory grid investment costs from those who benefit (1.2) 
Mandate systematic evaluation and implementation of alternatives (1.3) 
Designate strategic corridors and zones (2.1) 
Deploy Establish grid code requirements for demand connection (4.1) 
Set minimum application requirements (4.2) 
Establish differentiated connection terms for large loads (4.3) 
Establish a transparent methodology for the allocation of connection costs (4.3) 
Prioritise connection applications (4.2) 
Develop, publish and integrate hosting capacity maps (4.2) 
Develop a framework for phased connection agreements (4.3) 
Use locational signals and spatial planning to steer new connections (4.3) 
Establish fast-track connection procedures within strategic corridors and zones (4.2) 
Introduce dynamic operating envelopes (4.3) 
Operate Require dynamic ratings and dynamic operational limits (5.3) 
Establish an actor-neutral aggregation framework (6.1) 
Establish direct-control and interruptibility programmes for large flexible loads (6.2) 
Mandate or incentivise grid-enhancing technologies (5.3) 
Enable direct coordination of distributed assets (6.2) 
Define standardised local-level services and quantify needs (6.3) 
Mandate real-time operational frameworks for stability in systems with inverter-based resources (5.1) 
Adopt curative congestion management (5.3) 
Enable Mandate public disclosure of decision-making (7.1) 
Ensure transparent and equitable cost allocation across consumer groups (9.2) 
Introduce output- and performance-based revenue regulation (7.2) 
Adopt TOTEX cost treatment (7.2) 
Implement community benefit schemes for infrastructure hosting (9.3) 

What to keep in mind

Where data centres are required or choose to supply part of their own power, on-site generation does not default to clean sources, and clear rules on captive generation help keep it from locking in fossil fuels. If anticipated demand does not materialise, the cost of grid investment made for it can fall on other users, which strengthens the case for financial commitments from large-load applicants and for modular solutions such as solar and storage that can scale with demand. Rules written for data centres often apply equally to other large loads, such as electrolysers and electrified industry, so requirements are best designed for large loads in general. Flexibility commitments only deliver if they are contractual, enforceable and verified in operation. 

Good practices and further reading

Examples of good practice are linked from the relevant measure pages, including those on large-load connection terms, flexible connections and data centre funding for distributed flexibility. Additional key resources are listed below.

Continue reading

Continue through the guide with the next article.

Challenge brief: tackling connection queues