Why this recommendation matters
Connection processes were built for a slower, more centralised system and cannot keep pace with the volume and variety of applications they now receive. Existing processes struggle with rapid renewables deployment alongside rising demand from EV charging, heat pumps and air conditioning, industrial electrification and data centres. In the United States data centres typically wait three to seven years for connection, far longer than the 18 to 24 months needed to build the facility. In Europe, grid connection often takes more than five years, against one to two years each for permitting and equipment delivery, and has become the main impediment to large-scale electrification projects. Delays, opaque queues and inconsistent requirements create uncertainty for investors and end users, while also making grid planning less efficient. Misalignments between connection availability and asset reinvestment timelines can also leave companies with limited alternatives to reinvesting in fossil assets, and ultimately to greater carbon lock-in.
This recommendation calls for modernising how connections are requested, assessed, approved and delivered. Applications are cheap to lodge and cost little to maintain, so developers submit early, submit often, and hold positions across multiple locations while they decide which project to build.
Capacity is then reserved for projects that may never proceed, while viable projects wait behind them. Capacity in the queue should instead be held for projects that are progressing towards construction. Digitalising applications and publishing queue positions, available hosting capacity and processing timelines can, among other actions, reduce friction and make connection decisions faster and more predictable.
Faster and more predictable connection lowers financing risk and allows new supply and demand to come online in a timely fashion. This allows electrification efforts and new economic activity to proceed as planned. Clearing queues of non-viable applications frees capacity that was reserved rather than used, while tiered and batched application assessment concentrates scarce engineering resources where they have the greatest impact. Published hosting capacity and transparent queues, generally provided by grid companies or regulators, also improve planning by giving operators a clearer view of where demand and generation are heading, and they support security of supply by bringing clean capacity online in time to displace higher-carbon alternatives.
How to act on this recommendation
Stage 1
Regulators and policy makers should modernise and streamline the basic connection process.
Minimum application requirements should ensure that only serious, sufficiently developed projects can enter the process, through evidence of site control, technical data and financial commitment. Grid companies should be empowered to remove non-viable projects from the queue, for example through milestone-based management. The connection process should be designed with large loads in mind, since speculative applications from large loads are impactful on the size of connection queues. Small assets should be given simplified pathways proportionate to their limited system impact. Applications should be online-only via a registration platform that allows applicants to submit documentation and track progress. System impact study requirements should be tiered by impact and batched where possible. This work connects to the permitting reforms in recommendation 3.1; often the same authorities are involved, and the processing of application should be coordinated among them.
Stage 2
Actively manage scarce capacity.
Grid companies should develop, publish and integrate hosting capacity maps so that developers can see where capacity exists before applying, and extend digitalisation across the entire connection process from start to finish, including one-stop interfaces and automated assessment of standard applications. Coordination between transmission and distribution should be formalised for connection requests whose impacts extend from one to the other; this becomes increasingly important as distributed energy resources become more widespread. First-come, first-served allocation should give way to prioritisation of applications according to readiness and system value. These reforms connect to the data governance efforts under recommendation 7.3.
Stage 3
Link connection management more deeply to system operations.
Grid companies should move from static published maps of hosting capacity to a dynamic, operational capability reflecting real-time conditions. This depends on the observability and real-time modelling and control in objective 5, and provides the information layer beneath the dynamic operating envelopes in recommendation 4.3. In addition, projects in designated strategic corridors and zones should be fast-tracked, building on the spatial planning in recommendation 2.1. At this stage, the connection process as a whole can be made subject to binding maximum timelines with accountability mechanisms, provided that the relevant authorities are adequately resourced.
Core measures
Implementation considerations
Faster, more transparent connection processes are broadly supported, but disagreements emerge over how the costs and risks of reform are shared. Developers, end users and grid companies all gain when viable projects connect sooner and queue uncertainty falls. However, interests may diverge on how to allocate costs when a new connection triggers a grid upgrade, or when a project does not materialise or only partially does so. Grid companies may prefer to allocate all costs to the new connection that triggered the upgrade as it is procedurally simpler, and may want greater financial commitment from projects in the queue to mitigate the risk of stranded assets, although this is influenced by the regulatory incentives grid companies have for (anticipatory) grid buildout (see recommendation 7.2). Developers, meanwhile, tend to want faster access, fewer procedural requirements and lower financial commitments, and to reduce their exposure to the risk of penalties when a project fails to fully complete. End users may generally be reluctant to carry a share of the upgrade costs triggered by a new connection, particularly in the absence of a fair, transparent framework for allocating such cost sharing. They may also prefer a more stringent financial commitment regime, as the costs of stranded assets tend to be socialised in grid tariffs. Large industrial consumers typically value connection certainty far above the flexibility or capacity payments on offer, which are small against their total investment, so financial incentives tend to work better as a supplementary benefit than as the primary driver of participation.
A key implementation challenge is ensuring that connection reforms do not disproportionately favour well-capitalised actors. Mature developers welcome milestone-based queue management, deposits and readiness criteria because they eliminate speculative applications. However, whose same requirements can exclude smaller developers, municipal actors and community projects with limited capital and administrative capacity. Requiring planning permission before an application can be lodged improves queue quality, but can also slow development and reduce the system operators’ visibility of future demand. Queue discipline should therefore be paired with proportionate requirements, staged deposits, exemptions or targeted support for public-interest and community projects, and clear, accessible information. Where connections are prioritised on multiple criteria, sector-specific treatment may be needed to reflect differences in emissions and fuel-switching benefits.